Ash and Dirty Water Diversion System

Origin Energy

SNK Group was awarded the tender to construct an environmental water management system at Eraring Power Station.


This entailed:

  • Excavation and haulage of earth for access to in-service storm water system and pit construction.

  • Concrete settling pits were then formed and poured, including blinding slab and weirs.

  • Poly pipe welding and install for interconnecting pump lines.

  • Procure and install two electric transfer pumps, including high voltage electrical connection into station switchboard.

  • Instillation of handrails, signage, Armco railing and lighting around perimeter of works.


The project was completed successfully on time and within budget with zero incidents.