JAN 2023 - CURRENT
Eraring Power station Ash Dam Southern Embankment Stabilization Project – Borrow Pit
Origin Energy – Eraring Power Station
Details of the Project:
Vegetation clearing and grubbing of nominated area
Construction of haulage road to Menards site
Erosion and sediment control for entire site
Operation of Borrow Pit site excavating, crushing, screening and stockpiling rock design area of 430,000 m3 of rock with a maximum particle size of 150mm in diameter
Excavation and stockpiling of material will be undertaken in advance of the commencement of Ground Improvement (GI) works to ensure sufficient volume of material is maintained for the continuation of the SES Project