Dust Supression and Water System for Ash Dam

Origin Energy

In 2015 SNK Group was contracted by Origin Energy to carry out the supply and installation of a dust suppression and water transfer system for the Ash Dam at Eraring Power Station.


Key features of this project were:


  • Survey and set out of infrastructure.

  • Design and sizing of pumps and pipework to meet the evolving site requirements.

  • Design and construction of mobile canon trailers.

  • Installation of various staging tanks and pipework.

  • Commissioning and scheduled maintenance of the systems as well as ongoing evolution.


This package of works involved over 2.6km of pipeline, installations of 24 water storage tanks, 2 by 50,000 litreholding tanks and 6 pump sets around the Ash Dam. The $1.26m project was completed successfully on time and within budget with zero incidents.